Construction Projects and Road Closures
92nd Ave Electrical Undergrounding Project
Sturgeon Electric, working for Xcel Energy, sets a new light pole on 92nd Ave as part of the 92nd Ave undergrounding project. This project will enhance the beauty of 92nd Ave by removing the overhead power lines and placing them underground. The design of this project began in late 2020 and was moved into construction in early 2022. The construction phase for Xcel was completed around by the mid part of 2024. Once Xcel has removed their facilities from the existing power poles, the other utilities such as Comcast, CenturyLink and others will relocate as well allowing the poles to be removed.
2024 Completed Projects
Project | Location | Status |
2024 Waterline - Old Town Phase 1 |
W 90th Place, Clay Street, Elm Court |
The City will be selecting a contractor to replace the failing water lines in the Old Town neighborhood. The south portion of the neighborhood will be done this year and the north portion will be done the following year. |
Crosswalk Installation |
W 96th Ave & Elm Ct |
In an effort to increase the safety of children walking to Federal Heights Elementary School the City has contracted RoadSafe to install a crosswalk at W 96th Ave & Elm Ct. This will include a Rectangular Rapid Flashing Beacon (RRFB) Pedestrian Crosswalk System as well as alterations to the striping of the road. |
Street Paving |
Camenisch Way, Pecos St,
Orleans St, Orleans Ln, Rampart St, Mandel St, Royal St, W91st Pl |
The City contracted Asphalt Specialties to do a mill and overlay in the Monticello neighborhood, and Pecos St. A full depth reclamation was done along Camenisch Way. This project also included the addition of bike lanes and related signage along both sides of Pecos Street from 88th to 85th. A future project will continue the bike lanes from 85th to 84th. |
Future Planned Construction Projects
Project | Location | Status |
2025 Waterline - Old Town Phase 2 |
W 90th Place, Clay Street, Elm Court |
The City will be selecting a contractor to replace the failing water lines in the Old Town neighborhood. This phase will include 91st Ave, 91st Pl, and Elm Ct from 91st Ave to 92nd Ave. |
2024 Asphalt Patching |
City Wide | The City contracted EVH Enterprises to remove and replace failing or damaged sections of asphalt throughout the city. |